Water Line Inspections

In This Section

    Project Construction, Inspection and Testing

    Water line construction can only be performed by a North Carolina licensed contractor. Once construction begins, construction inspectors will periodically inspect the water line to ensure that the line and its appurtenances are being constructed as designed and as to the Standard Details and Specifications. As construction nears completion, the contractor is required to perform pressure testing under the observation of the inspector. Also, the contractor is required to schedule disinfection testing with the Water Resources Department by contacting the project inspector. Upon construction completion, the developer, engineer and contractor are required to complete the project close-out procedure before a final inspection can be done.

    Project Close-out Procedure

    In order to obtain final approval and acceptance of a water line project and to authorize the release for domestic or fire protection service, Water Resources Department's office needs to receive the following documents:

    1. Certificates of Completion
    2. Recorded Water Line Easement Documents (select document as applies, print on LEGAL-size paper, and submit the appropriate Buncombe County Recording Fee made payable to Buncombe County).  If these documents are not printed on Legal-size paper, Buncombe County will charge an additional fee.
    3. Recorded Easement Plat (see plat requirement checklist)
    4. AutoCAD Record/As-built Drawing File on CDROM and Sealed Paper Copy (see record/as-built requirement checklist)
    5. List of Subdivision Lot 911 Addresses
    6. Back Flow Device Brand and Model Number

    View the Project Construction and Close-out Procedure flow chart.

    Adobe Acrobat Reader is required to view the following documents:

    Close-out Checklist for Completed Projects
    Engineer’s Certificate of Completion
    Contractor's Certificate of Completion
    Owner's Certificate of Completion
    Corporation Easement Document
    Limited Liability Company Easement Document 
    Individual Easement Document
    Plat requirement checklist
    Record/as-built requirement checklist
    Construction Process and Close-out Procedure

    Contact Information


    Technical requirement questions

    Water Resources Department
    P. O. Box 7148
    Asheville, NC 28802
    7:30 a.m.-5:30 p.m., Monday-Thursday

    ATTN: Senior Project Engineer, Sonia Salgado, PE
    (828) 259-5534
    ssalgado@ashevillenc.gov

    ATTN: Project Engineer, Mark Letterman
    (828) 232-4589
    mletterman@ashevillenc.gov

    Close-out procedure questions
    City of Asheville
    Water Resources Department
    ATTN: Gloria Smith
    P.O. Box 7148
    Asheville, NC 28802
    Phone 1: (828) 259-5403
    Phone 2: (828) 259-5955
    gsmith@ashevillenc.gov


    Inspection questions within the city limits & ETJ


    Water Resources Department
    ATTN: Engineering Services Manager, Chad Pierce, PE
    P. O. Box 7148
    Asheville, NC 28802
    7:30 a.m.-5:30 p.m., Monday-Thursday
    (828) 259-5420
    cpierce@ashevillenc.gov


    Delivery address

    Water Engineering / Water Resources
    ATTN: Gloria Smith
    Public Works Building
    161 South Charlotte Street
    Asheville, NC 28801

    Stay Connected