Happening Now
January 3 – Due to the extensive utility re-construction required and ongoing Helene Response efforts, Hiawassee Street between Rankin Avenue and North Lexington Avenue will be temporarily repaved. This is a temporary solution, necessary to restore access while planning for a permanent upgrade to the utility and stormwater system. The timing of the repaving will be dependent on weather, availability of materials, and on the prioritized road resurfacing needed from our Helene Response.
Staff are actively collaborating with utility partners to identify conflicts and to finalize the utility relocation designs, and ensure the infrastructure improvements align with the upgraded stormwater system previously identified. Road closure for permanent stormwater construction is anticipated to begin after utility work is completed.
We appreciate your patience and support as we work toward long-term improvements for the area. Stay tuned for updates on the construction timeline.
Background
Stormwater crews have been working diligently since May 9 after heavy rainfall impacted the area. Crews have identified a significant number of utility conflicts in the area, preventing crews from installing the new stormwater lines. Staff are analyzing the possibility of rerouting and upgrading the line down Hiawassee St. from Rankin to North Lexington.
Timeline
May 9, 2024 – Stormwater system was damaged due to the heavy rainfall
June 6, 2024 – Construction began
July 9, 2024 – Utility exploration work
September 27, 2024 – Tropical Storm Helene
Winter 2025 – Temporary paving of Hiawassee Street
Winter 2026 – Construction to relocate utilities expected start
Past Updates
July 9, 2024 – As of July 9, stormwater staff and crews are working to determine the new layout necessary for the stormwater drain. The preliminary work of location and mapping of utility lines started this week. Pending any unforeseen utility or relocation conflicts or weather complications, crews can begin laying stormwater pipe early next week.
June 6, 2024 – Hiawassee St. between Rankin Ave. and N. Lexington will now be closed until August 7. Crews have identified a potential location for the upgraded stormwater system down Hiawassee St. to North Lexington. The City is now working with other utilities to ensure this location is feasible and then will begin construction.
Project Contact
Derek Wainscott
Storm Water Division Manager
City of Asheville