Happening Now

The City of Asheville Water Resources has received a total of $4 million in funding to help determine the water service line material on both sides of a water meter –  the utility- and customer-owned sections. The funding will allow the City to replace any water service lines that are found to be lead or galvanized iron pipe on both the utility- and customer-owned sections.

The Water Resources Department has developed a plan for the Shiloh Community customer outreach. The plan includes community meetings, outreach via  phone calls and text messages, mailers, and door hangers. Customer participation is necessary to be included in this project. Although participation is crucial to the success of the project, participation is voluntary.

For a comprehensive explanation of this project and the Water Resources Department’s overall service line inventory initiative, visit the  Shiloh Community Project presentation or the City of Asheville Lead Awareness Page

Why Shiloh?

This area was chosen because it meets the following criteria established by the City and the terms of the grant:

  • Water mains that serve these areas were installed when lead and galvanized pipe were commonly used for service line material.
  • Homes in the area were, for the most part, built between the 1930s and the 1960s.
  • Shiloh is considered a historically disadvantaged area, per the City’s Climate Justice Map and the state of North Carolina’s Department of Water Infrastructure Map.

Shiloh Community Phase 1: Streets involved in the Inventory and Replacement Project

  • Taft Avenue
  • Jeffress Avenue
  • Grant Avenue
  • Century Boulevard
  • Gaines Avenue
  • Hampton Street
  • Caribou Road from Hampton Street Intersection to Ardmore Street

Shiloh Community Phase 2: Streets involved in the Inventory and Replacement Project

  • Southern side of Shiloh Road
  • Booker Street
  • Forest Street
  • Seminole Street
  • Caribou Road from Forest Street to Hendersonville Road
  • Imperial Court
  • Deanwood Circle
  • Dawnwood Condominiums
  • Forestdale Street
  • Adamswood Road

Background

The federal Environmental Protection Agency (EPA) implemented the new Lead and Copper Rule Revisions (LCRR) in early 2021, requiring all public water utilities to develop a water service line inventory. The Water Resources Department had previously started a Lead Awareness Program that included free service line inspections and testing drinking water for lead.

Water Resources has applied for a total of $4 million in funding from the North Carolina Department of Water Infrastructure (NCDWI) for the replacement of lead and galvanized service lines. 


Shiloh Community Service Line Inventory and Replacement Project

Phase 1 Information

On April 30, 2023 Water Resources applied for $2 million in funding and NC DWI approved the City’s application in November 2023. Community outreach for Phase I began in January 2024, whose area is shown in maps below. Outreach included door hangers that provided information and an opportunity to sign up for participation in the project. Water Resources also attended two community meetings at the Linwood Crump Shiloh Community Center on February 5, 2024, and February 26, 2024, both of which included a presentation on the project. Staff shared project details and answered community members’ questions.

Phase 2 Information

On March 1, 2024, Water Resources applied for another $2 million in funding. NC DWI approved the City’s application on May 29, 2024. Community Outreach will begin in August 2024. Outreach will include door hangers that will notice community meetings and will provide information and options on how to sign up to participate in the project.  

Projection construction is not scheduled to begin until Winter of 2024-2025.


Timeline

Estimated Project Timeline
Task Estimated Completion Date
Phase 1 – Engineering and Investigation Efforts
City outreach to residents in the project area December 2023 – February 2024
Submittal of Engineering Report/Environmental Information Document and Bid and Design Package March 1, 2024
Prep of bid package while Engineering Report/ Environmental Information Document and Bid and Design Package are under review (if needed) January – April 2024

Approval of Engineering Report/ Environmental Information Document and Bid and Design Package

Contract for engineering services

City outreach to residents in the project area

Submittal of Engineering Report/ Environmental Information Document and Bid and Design package

Begin and complete inventory work while the Engineering Report/ Environmental Information Document and Bid and Design package are under review

Approval of Engineering Report/ Environmental Information Document and Bid and Design package

April 1, 2024

Waiting on Council approval- July 23, 2024 meeting

Ongoing

August 30, 2024

Ongoing

 

September 30, 2024

Phase 2 – Replacement Efforts
Advertise Project, Receive Bids, Submit Bid Information, and Receive ATA October 2024
Initial Desktop LSL Inventory Submittal to Public Water Supply Section October 2024
Execute Construction Contract(s) November 2024

Investigation Work Complete

Replacement Project Complete

December 2024

January 2025


Supporting Documents

City of Asheville Lead Awareness Page

Project of Scope of Work Submitted to State 12/1/23– Project scope will be updated to include Phase 2 of the project in August 2024.

Project Map of Phase 1 AreaMap of Phase 1 Project Area – Taft Avenue, Jeffress Avenue, Grant Avenue, Century Boulevard, Gaines Avenue, Hampton Street, Caribou Road from Hampton Street Intersection to Ardmore Street.

Project Map of Phase 2 Area Map of Phase 2 Project Area – Southern side of Shiloh Road, Booker Street, Forest Street, Seminole Street, Caribou Road from Forest Street to Hendersonville Road, Imperial Court, Deanwood Circle, Dawnwood Condominiums, Forestdale Street, Adamswood Road.


Contact Information

Brenna Cook, Compliance Manager – City of Asheville Water Resources Department
828-259-5962

Clay Chandler, Public Information Officer – City of Asheville Water Resources Department
828-259-5419


Related Services

Pay your water bill

How to pay your water bill, with convenient online, automatic draft, mail or in person options.

Rates and Fees

View a list of water consumption charges for various types of activities, as well as information on other water fees.

Sewer services

Find out about sewerage services provided by Metropolitan Sewerage District (MSD), and how to ask questions and find additional information.

Water quality and advisories

View the yearly water quality report, current advisories and outages, as well as register to be notified of advisories in your area.

Related Departments

Bee Tree reservoir

Water

The Water Resources Department (WRD) provides drinking water to Asheville and the surrounding areas. WRD owns and operates three drinking water treatment plants, and maintains over 1700 miles of water lines in the distribution system. We’re working for you! To receive emergency texts directly from Buncombe County for breaking health and safety news text BCALERT on your [...]

X